Project tendered by Havant Borough Council to refurbish the existing sports pavilion and construct a circular extension.

CLIENT
Havant Borough Council

PROJECT VALUE
£930,000

PROJECT
Front lawn recreation ground

DATE
March 2017 - January 2018

Specifications

  • Project tendered by Havant Borough Council to refurbish the existing sports pavilion and construct a circular extension
  • Works tendered as a build only project to Architect’s specification
  • Close collaborative working to agree detailing on site as works progress
  • Samples supplied for brick matching and floor finishes for approval
  • Site set up with temporary office, storage, toilet and welfare units
  • Construction site with fenced boundary, locked gate and close focus on security to prevent unauthorised access since adjacent field remained open to public
  • Environmental initiatives include recycling demolished walls as hardcore and segregating waste
  • Refurbishment works required the complete demolition of internal partitions and construction of blockwork walls to suit new design layout
  • Installation of new toilet and shower facilities in changing room for players and officials
  • Provision of DDA compliant facilities
  • Plastering and tiling to wet areas and redecoration throughout
  • Installation of new air handling unit and duct work to improve ventilation
  • Concurrent programme of works with new build construction of circular extension
  • Groundworks and drainage installations
  • Stepped concrete foundations to suit sloping site
  • Block and beam construction floor with underfloor heating
  • Block and brickwork walls with aluminium double glazed windows
  • Bespoke structural steelwork
  • GPR roofing system
  • Security protection with innovative lintels including integral steel shutters
  • All new doors throughout with satin stainless steel ironmongery
  • New electrical power, lighting, fire alarm, intruder alarm and CCTV installations
  • Provision of staff tea‐point and refreshments kitchen with roller shutter
  • External improvements to resurface carpark to new falls
  • Install steps, ramped access, handrails and bicycle hoops
  • Regular meetings on site throughout construction including constant quality control review
  • Close financial monitoring with regular appraisals provided to Architect
  • Project completed to Building Control requirements
  • Works handed over on programme
  • Handover meeting on completion with full training supplied on all equipment installed
  • Health and Safety File, Operations and Maintenance Manual handed over with all certification