Customer: Legoland
Project Title: Installation of new Pirate Landings ride
Project Value: £200,000.00
Project Specification:
- Extensive groundworks to create pit and pad foundations
- Extremely tight tolerances for installation of reinforcing steelwork
- Critical performance criteria for grout and pumped concrete
- Extensive surfacing, fencing and bespoke joinery works
- Project to architect’s design and structural engineer’s specification
- Co-ordination of key electrical & gate supply sub-contractors
- Liaison with specialist crane lifting and ride installation engineers
- CDM project with close scrutiny of Health & Safety
- Work undertaken to tight programme to complete before park opens
- Project progressed under demanding winter weather conditions